Schedule
- Conceptual Design: Summer/Fall 2023
- Preliminary Design: Winter 2023/2024
- Final Design: Summer/Fall 2024
- Utility Relocation: Spring 2025
- Construction Begins: Spring 2025
- Construction Ends: Summer 2025