114th Street, West Center Road to Pacific Street
The underlying pavement on 114th Street is in poor condition and needs to be replaced. This project would reconstruct the existing roadway from West Center Road to Pacific Street.
Project Features
Improvements
- Reconstruct existing pavement on 114th Street
- Install new curbs and gutters along the roadway
- Evaluate and reconstruct curb ramps and sidewalks to meet ADA standards
- Enhance accessibility and safety for pedestrians
Schedule
-
ROW Process: April 2028
-
Utility Relocations: March 2029
-
Construction: March 2030
-
Construction Ends: July 2031